Share.

    22 Kommentare

    1. BAM, and your money’s gone.

      And you have no idea when you will get your completed hospital.

    2. Different-Class1771 on

      For some reason when I was scrolling I thought the headline was about Bam Margera not meeting his mam, April.

    3. Gentle reminder that the person who signed off this fiasco has been promoted to Minister for Finance 

    4. ToysandStuff on

      This isn’t really a problem. All they need is another 15-20 billion euros of taxpayers money and they’ll get back on track. No worries

    5. Late AND over budget is an incredible feat. Can’t think of many that can pull it off. Hats off to all involved, a great team effort.

    6. By the time this is built every child on earth will be an adult, even the ones that aren’t born yet

    7. GrahamR12345 on

      At the rate they are going will need an Adult hospital to treat all those kids that would have been treated in that hospital if it was built on time…

    8. HongKongChicken on

      Guys, next time I want to be the one who posts „BAM and the X is gone“ for the one millionth time in desperate hopes of fake internet points

    9. StrongCelery on

      This was doomed to failure from the start as the government never fully specified the requirement when initially put out to tender. A friend of mines company refused to provides sensible quote for the air handling requirement because it was inadequately specified (they did quote but at a price that was never going to fly) He knew it would overrun by a long margin and he would be involved in fight after fight for money. He decided they should concentrate on data centres and the like and let his competitors get tied up in knots on this.
      I have no idea who this BAM crowd are but if the rest of the hospital was as poorly specified then you can see why the overrun happened. That said they took the contract and thus are equally culpable. Harris should be thrown out on his ear for this and BAM barred from any future infrastructure projects.

    10. croquetamonster on

      This has taken so long that the trendy architecture that made it so expensive is now tacky and outdated. A monstrosity.

    11. JonShannow07 on

      I am sure BAM have cast iron receipts for all their delays, otherwise contracts would penalise them.

      So the fault lays with the HSE no matter how you look at it, shoddy loose initial contract and/or the 1000s of changes to the plans which BAM can point to whenever there is a delay.

    12. Specific-Manager-125 on

      If we actually had some political accountability Harris would be sacked and voted out for such eye boggling incompetence to begin with

    13. CounterSea1402 on

      Pretty sure this the Irish equivalent to Basílica de la Sagrada Família; they’ll still be building it in 140 years.

    14. DuckyD2point0 on

      This is BAM, so why is this news.

      The fact the fuck over subcontractors to the point of not paying them and threatening them with court should be what’s spoken about. They literally have the name „THE SUBBY BUSTERS“.

    15. Such_Baker8707 on

      Worst thing is that these jokers can’t even be blacklisted from government contracts going forward

    Leave A Reply